Client: ERG
Date: January ’20 – March ’21
Location: Dungiven, Co. Londonderry

Project Details:
The Contract was completed for ERG.  This was a joint venture project completed along with Mills Contracts Ltd. RES Ltd. provided Project Management on the contract.  Works completed as part of the Design & Build Contract were as follows:

  • Installation of 13 Turbine foundations
  • Installation of 13 Hard stand areas including blade laydown areas and crane assist pads
  • Installation of 6 culverts along the access roads
  • Installation of Access tracks
  • Installation of Substation building
  • Installation of SuDS features throughout the site
  • Installation of Temporary Compound

 

 