Client: Omexom
Date: August 2021 – November 2021
Location: Stackallen, Slane, Co. Meath

Project Details:
The project was completed for Omexom.  Works involved the installation of transformer bases which formed an extension to the existing ESB substation.

Works on site included the following:

  • Construction of access site tracks
  • Construction of transformer bunds
  • Construction of auxiliary bunds
  • Installation of inter-connector cable
  • Installation of temporary compound
  • Installation of crane hardstand area
  • Installation of palisade fencing