Client: Powercomm
Date: April 2021 – October 2021
Location: Kells, Co. Antrim

Project Details:
The contract was completed for Powercomm.  The overall client for the site was ABO Wind.  The main works on site was the construction of a substation to facilitate the battery energy storage site located adjacent to the substation site.

Works on site included the following:

  • Excavation of foundation for substation building
  • Installation of bunded basement within the substation
  • Construction of the substation building
  • Construction of transformer bases
  • Installation of ducting around the building
  • Installation of drainage around the building
  • Installation of palisade fencing
  • Completion of groundworks and finished surfaces around the substation building.

Similar Projects

Belcoo 33/11kV Substation

Poulaphouca Remediation

Clady Public Realm

Smulgedon Control Building

Corby Knowe Met Mast

Broadway Flats Substation

Ardstraw Substation

Evishagaran Turbine Delivery Route

Gorman Transformer Bases

Killala BESS