Client: NIE Networks
Date: July – November 2020
Location: Limavady, Co. Londonderry

Project Details:
Works were completed at Hoechst Fibres 33/11kV Live Substation located outside Limavady and included:

  • The removal of existing brick boundary walls around the substation while maintaining the security of the substation.
  • The construction of a new 11kV control room which forms part of the new boundary of the substation.
  • Installation of flood light bases and floodlights with associated ducting
  • Installation of earth matting around the substation
  • Installation of Palisade fencing around the external area of the substation
  • Installation of a new Paladin gate at the entrance to the substation
  • Improvement of the general surface of the compound by laying new aggregate to the surface

Similar Projects

Belcoo 33/11kV Substation

Poulaphouca Remediation

Clady Public Realm

Smulgedon Control Building

Corby Knowe Met Mast

Broadway Flats Substation

Ardstraw Substation

Evishagaran Turbine Delivery Route

Gorman Transformer Bases

Kells Substation