Client: NIE Networks
Date: Jan-Feb ’19 & June-Jul ’19
Location: Larne North Substation, Larne, Co. Antrim
Project Details
Works were completed over 2 phases. The contract involved the refurbishment of existing fence and surfaces in and around the substation. The following was completed on site:
- Removal and disposal of existing palisade fence
- Installation of new Palisade fencing included concrete base
- Installation of concrete lighting tower bases
- Installation of new steps for Control building and Scada room
- Installation of bases for new steps at transformers
- Re-stoning of the surface of the substation