Client: ERG
Date: January ’20 – March ’21
Location: Dungiven, Co. Londonderry

Project Details:
The Contract was completed for ERG.  This was a joint venture project completed along with Mills Contracts Ltd. RES Ltd. provided Project Management on the contract.  Works completed as part of the Design & Build Contract were as follows:

  • Installation of 13 Turbine foundations
  • Installation of 13 Hard stand areas including blade laydown areas and crane assist pads
  • Installation of 6 culverts along the access roads
  • Installation of Access tracks
  • Installation of Substation building
  • Installation of SuDS features throughout the site
  • Installation of Temporary Compound

 

 

Similar Projects

Broadway Flats Substation

Ardstraw Substation

Evishagaran Turbine Delivery Route

Gorman Transformer Bases

Kells Substation

Killala BESS

Gortin Glens Equestrian Trails

Aghada BESS

Rigged Hill Access Road

Arney Battlefield Community Trails