Client: NIE Networks
Date: Jan-Feb ’19 & June-Jul ’19
Location: Larne North Substation, Larne, Co. Antrim

Project Details

Works were completed over 2 phases.  The contract involved the refurbishment of existing fence and surfaces in and around the substation. The following was completed on site:

  • Removal and disposal of existing palisade fence
  • Installation of new Palisade fencing included concrete base
  • Installation of concrete lighting tower bases
  • Installation of new steps for Control building and Scada room
  • Installation of bases for new steps at transformers
  • Re-stoning of the surface of the substation