Project Details: The project consisted of the construction of 7 turbine wind farm on elevated site overlooking Larne. Works included the following:
- Construction of Site Tracks
- Excavation of turbine bases
- Installation of turbine foundations
- Installation of Cable route
- Construction of Control Building
- Installation of Culverts
- Installation of SuDS drainage
- Installation of Passing bays on access road
- Installation of concrete apron at Site entrance