Project Description

Client: NIE

Contract Period: 5 months

Location: Coalisland and Dungannon


Project Details:

  • 2No 275KV terminal Pylon foundations
  • Precast driven piles , 550m3 concrete & 40T of Rebar
  • 2No 110KV terminal Pylon foundations
  • Precast Driven Piles, 60m3 of concrete, 6T of Rebar
  • Permanent and temporary access Roads
  • 275KV work had to be completed beneath Live overhead lines
  • Assembly and erection of 110KV towers

Similar Projects

Broadway Flats Substation

Ardstraw Substation

Kells Substation

Hoechst Substation

Garvagh Main Substation

Brett Martin Cable Trenching

Larne North Substation

Portaferry Sewage Treatment

Hannahstown Substation

Coolkeeragh Extension