Project Description

Client: NIE

Contract Period: 5 months

Location: Coalisland and Dungannon


Project Details:

  • 2No 275KV terminal Pylon foundations
  • Precast driven piles , 550m3 concrete & 40T of Rebar
  • 2No 110KV terminal Pylon foundations
  • Precast Driven Piles, 60m3 of concrete, 6T of Rebar
  • Permanent and temporary access Roads
  • 275KV work had to be completed beneath Live overhead lines
  • Assembly and erection of 110KV towers