Project Description

Client: Infinis

Contract Period: June 2015 to November 2016

Value: £10 million

Location: South Lanarkshire (7km east of Muirkirk, East Ayrshire and 4km west of Douglas)


Project Details:

Galawhistle Wind Farm (Phases 1 & 2) was built by Gael Force Renewables which was a Joint Venture between William & Henry Alexander (Civil Engineering) Ltd, McLaughlin & Harvey Ltd and Barr Holdings Ltd. The works under both phases included;

  • 22 No Vestas Turbine Foundations
  • 6 miles of New Site Roads
  • 22 No. Crane Hardstands
  • 10 No. Culvert Crossings
  • Electrical Balance of Plant (EBOP) Works involving design, cable trenching and Laying, Substation & Control Building
  • Scottish Power Platform